Farakka Print

Address P.O. Nabarun-742 236,Dist. Murshidabad,West Bengal (STD-FKN-03485, KJT-03512)
Telephone (STD-FKN-03485, KJT-03512) KJT -224241 FKN - 252131
Fax KJT-26449
Email
Approved capacity 2100 MW
Installed Capacity 2100 MW
Location Murshidabad, West Bengal
Coal Source Rajmahal Coal Fields of ECL
Water Source Farakka Feeder Canal

Beneficiary States

West Bengal, Bihar,Jharkhand, Orissa, Sikkim, Assam, Tripura and Damodar Valley Corporation.
Approved Investment Stage I: Rs. 730.93 Crore
Stage II: Rs. 2453.29 Crore
Unit Sizes Stage - I: 3x 200 MW
Stage -II: 2x 500 MW
Stage -III expansion of Farakkaa STPP is approved with
the addition of one 500 MW unit.
Units Commissioned

Unit -I 200 MW January 1986
Unit -II 200 MW December 1986
Unit -III 200 MW August 1987
Unit -IV 500 MW September 1992
Unit -V 500 MW February 1994
Unit -VI 500 MW March 2011

International Assistance IBRD
KFW
Italian assistance, Banker's Trust co.
EXIM Bank, Japan, IDA

Coal Based Power Station

[ Singraulli | Korba | Ramagundam | Farakka | Vindhyachal | Rihand | Kahalgaon | NTCPP | Talcher Kaniha | Unchahar | Talcher Thermal | Simhadri | Tanda | Badarpur | Sipat ]


Gas/Liq. Fuel Based Power Stations

[ Anta | Auraiya | Kawas | Dadri | Faridabad | Jhanor-Gandhar | Rajiv Gandhi CCPP Kayamkulam ]


Hydro Based Power Station

[ Koldam | Loharinag Pala | Tapovan Vishnugad ]


Power Plants With Joint Ventures

[ Durgapur | Rourkela | Bhilai | RGPPL ]

Back