Simhadri Print

Address P.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh
Telephone (STD-08924,STD-Vizag-0891) - 243001
Fax 243092
Email
Location Near Pittavanipalem Village,Dist. Vishakhapatnam, Andhra Pradesh
Govt. approved date 24.07.1997 (Zero date 8.7.1997)
Approved Capacity/Installed Capacity 2000 MW
Plant Configuration 4X500 MW
Land Availability 3384.24 acres (entire land)
Coal Source Kalinga Block of Talcher Coal fields in Orrisa
Water Source Yeluru canal for sweet water, Sea water for CW system.
Beneficiary States Andhra Pradesh (100%) .
Approved Investment Rs.3650.79 Cr.(I Qtr.97).
Associated Transmission System Implemented by APTRANSCO.
Units Commissioned Unit-I Commissioning: Feb 2002
Unit-II Commissioning: Aug 2002
Unit-III Commissioning: Mar 2011
Unit-IV Commissioning: Mar 2012
International Assistance JBIC

Coal Based Power Station

[ Singraulli | Korba | Ramagundam | Farakka | Vindhyachal | Rihand | Kahalgaon | NTCPP | Talcher Kaniha | Unchahar | Talcher Thermal | Simhadri | Tanda | Badarpur | Sipat ]


Gas/Liq. Fuel Based Power Stations

[ Anta | Auraiya | Kawas | Dadri | Faridabad | Jhanor-Gandhar | Rajiv Gandhi CCPP Kayamkulam ]


Hydro Based Power Station

[ Koldam | Loharinag Pala | Tapovan Vishnugad ]


Power Plants With Joint Ventures

[ Durgapur | Rourkela | Bhilai | RGPPL ]

Back