NTPC Simhadri

AddressP.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh
Telephone(STD-08924,STD-Vizag-0891) - 243001
Fax243092
Approved capacity2000 MW
Installed Capacity2000 MW
LocationNear Pittavanipalem Village,Dist. Vishakhapatnam, Andhra Pradesh
Coal SourceKalinga Block of Talcher Coal fields in Orrisa
Water SourceYeluru canal for sweet water, Sea water for CW system.
Beneficiary StatesAndhra Pradesh (100%) .
Approved InvestmentRs.3650.79 Cr.(I Qtr.97).
Unit SizesUnit-I Commissioning: Feb 2002
Unit-II Commissioning: Aug 2002
Unit-III Commissioning: Mar 2011
Unit-IV Commissioning: Mar 2012
International AssistanceJBIC
Govt. approved date24.07.1997 (Zero date 08.07.1997)
Land Availability3384.24 acres (entire land)
Associated Transmission SystemImplemented by APTRANSCO.
Associated Transmission SystemImplemented by APTRANSCO.
Plant Configuration4X500 MW