Loading...

Project Management (PM)

Recognizing the cost of time overruns, NTPC adopted Integrated Project Management Systems for all its projects and has successfully commissioned its projects (own) as well as of the clients ahead of schedules.

Services covered under Project Management include the following:

  • Establishing Integrated Project Management & Control System
  • Preparation and Review of Master Network for the project 
  • Review of Network for Procurement and Site Activities 
  • Review of adequacy of resources and indirect-direct cost tradeoffs
  • Project Monitoring using PERT and Primavera Tools

Experience in Project Management includes the following:

Sl.No.Client's NameName of the projectsServices ProvidedYear
25MPPGCL2X250 MW Satpura TPSAppointment of Project monitoring sevices group for 2X250 MW extn. Units 10 & 11 at SatpuraTPP2010
24MPPGCL2X600 MW Shree Singhaji TPP Stage-IProject monitoring services for 2X600 MW Shree Singhaji TPP Stage-1 at Dongalia, Dist. Khandwa.2010
23HPGCL2 X 600 MW Rajiv Gandhi Thermal Power Project at HissarProject management services2008
22Aravali Power Company Pvt. Ltd.3 x 500 MW Aravali STPP.Pre-award and post award engg., contract administration, QA&I, assistance during commissioning PG test & Corporate Monitoring services.2007
21NTPC Tamil Nadu Energy Co. Ltd. NTECL2 x 500 MW Ennore power projectDesign, Engg., contracting, monitoring, QA&I for setting up power plant2007
20IOCLHaldia RefineryProject Management work at Haldia Refinery for 11kV generation distribution system.2006
19DVC2 x 250 MW Extn. U-5&6 of Mejia and U-7&8 of Chandrapura TPS.Supply & installation of Primavera Proj. Mgmt.2005
18DVC2 x 250 MW Chandrapura TPSProj.Mgmt., Const. Mgmt. & FQA for 2 x 250 MW Chandrapura TPS extn., U-7&8.2005
17DVC2 x 250 MW Mejia TPSProj.Mgmt., Const. Mgmt. & FQA for 2 x 250 MW Mejia TPS extn., U-5&6.2005
16DPL300 MW Durgapur TPS unit-7Proj.Mgmt., Const. Mgmt. & FQA for Durgapur Project power station extn. Unit-7 (300 MW)2004
15WBPDCL1 x 250 MW Santaldih TPSProj.Mgmt., Const. Mgmt. & FQA for 1 x 250 MW Santaldih TPS.2004
14WBPDCL2 x 300 MW Sagardighi TPPProj.Mgmt., Const. Mgmt. & FQA for 2 x 300 MW Sagardighi TPS.2004
13CEACEA officeModernization of CEA building with low partition.2003
12Konaseema Oakwell EPS441 MW Konaseema CCPPOwners Engineer Services including site supervision2001
11NDMCSub-stationsCS for establishing 33 kV & 66 kV sub station2001
10Gujarat Mineral Development Corporation2x125 MW Akrimota Lignite based Power PlantSupervision during Construction & erection, Project Management2001
9Delhi Vidyut Board.300 MW Combined Cycle Power Project.Owners Engineer Services.1999
8Kerala State Electricity Board.128 MW Diesel PP at Kozhikode.Finalization of Contract, Detailed Engg., Inspection Services, Construction, Supervision.1997
7West Bengal Power Development Corporation Ltd.2X210 MW TPP at BakreswarProject management, QA& Inspection, FQA Services.1997
6Spectrum Power Generation Ltd.206 MW Kakinada Gas Based Combined Cycle Power Plant, Andhra Pradesh.Engineering, QA & Inspection, Contract & Procurement, Project Management, Site Supervision, Pre-commissioning services.1994
5India Oil Corpn. Ltd.3X25 MW Panipat Captive Thermal Power Station.Preparation of feasibility report, design, engineering, QA& Inspection, procurement, project management & site supvsn.1993
4Dubai Electricity & Water Authority.400 & 132kV transmission line construction.Turnkey supply and installation/constn. of 400kV & 132 kV Transmission line and up-gradation of existing 132kV line to 400kv.1991
3Karnataka Electricity Board.Transmission System.Engineering, Procurement, Project Management & construction of 400kV line loop-in loop-out.1990
2Bharat Aluminium Co.4X67.5 MW Captive TPS at Korba & associated 220KV transmission system.Design, Construction, Commissioning and Project Management.1984
1Neyveli Lignite Corporation.400 KV Transmission System including two 400 KV Substation.Design, Construction, Commissioning and Project Management.1984