Address | P.O. Rihandnagar-231 223,Dist. Sonebhadra, Uttar Pradesh |
Telephone | (STD-05446) - 242020-21 |
Fax | 242115 |
Approved capacity | 3000 MW |
Installed Capacity | Stage I : 1000 MW Stage II : 2000 MW |
Location | Sonebhadra, Uttar Pradesh |
Coal Source | Amlori Mines & Dudhichua Mines & Amloric Expansion Mines |
Water Source | Rihand Reservoir. |
Beneficiary States | Uttar Pradesh, Uttarakhand, Haryana, Punjab, Rajasthan, Jammu & Kashmir, Himachal Pradesh, Delhi and Chandigarh. |
Approved Investment | Rs. 2387.40Cr (Stage-I). Rs. 3451.97Cr (Stage-II). |
Unit Sizes | 5x 500 MW |
Units Commissioned | Unit -I 500 MW March 1988 Unit -II 500 MW July 1989 Unit -III 500 MW January 2005 Unit -IV 500 MW September 2005 Unit -V 500 MW May 2012 Unit -VI 500 MW |
International Assistance | United Kingdom |