Talcher Kaniha

NTPC Talcher Kaniha

AddressP.O. Deepshikha (Kaniha)-759 147 Dist. Angul, Orissa
Telephone(STD-06760) - 243252
Fax232423
Approved capacity3000 MW
Installed CapacityStage I : 1000 MW Stage II : 2000 MW (Under Construction)
LocationAngul, Orissa
Coal SourceTalcher Coal Field Lingraj Block.
Water SourceSamal Barrage Reservoir Samal Barrage Reservoir on river Brahmani
Beneficiary StatesOrrisa, Bihar, Sikkim, Assam, Tripura & Damodar Valley Corporation, WB, Jharkhand for Stage I AP, Kerala, Karnataka, TN,Pondichery for Stage II
Approved InvestmentRs.9241.01 Crore
Unit Sizes6 X 500 MW
Units CommissionedStage I
Unit - I : 500 MW February 1995
Unit - II : 500 MW March 1996
Stage II
Unit - III : 500 MW January 2003
Unit - IV : 500 MW October 2003
Unit Commissioned SheduleStage II
Unit - V : 500 MW May 2004
Unit - VI : 500 MW February 2005
International AssistanceIBRD French loan