Address | P.O. Vindhyanagar-486 885,Dist. Singrauli, Madhya Pradesh |
Telephone | (STD-VND-07805, SKTN-05446) - 244010 |
Fax | 244011 |
Approved capacity | 4760 MW (Stage-I 1260 MW + Stage-II 1000 MW + Stage-III 1000MW + Stage-IV 1000MW + Stage-V 500 MW) |
Installed Capacity | 4760 MW |
Location | Sidhi, Madhya Pradesh |
Coal Source | Nigahi Mines |
Water Source | Discharge canal of Singrauli Super Thermal Power Station. |
Beneficiary States | Madhya Pradesh,Chattisgarh, Maharashtra, Gujarat,Goa, Daman & Diu and Dadar Nagar Haveli. |
Approved Investment | Stage I & II- Rs.4053.42 Crore + Stage-III Rs. 4201.5 crs. |
Unit Sizes | Stage I: 6x 210 MW + Stage-II: 2x500 MW + Stage III: 2x 500 MW . |
Units Commissioned | Unit -I: 210 MW October 1987 Unit -II: 210 MW July 1988 Unit -III: 210 MW February 1989 Unit -IV: 210 MW December 1989 Unit -V: 210 MW March 1990 Unit -VI: 210 MW February 1991 Unit -VII: 500 MW March 1999 Unit -VIII: 500 MW February 2000 Unit -IX: 500 MW July 2006 Unit -X: 500 MW March 2007 Unit -XI: 500 MW June 2012 Unit -XII: 500 MW March 2013 Unit -XIII: 500 MW August 2015 |
International Assistance | USSR - Stage I World Bank under Time Slice loan - Stage II |